REFERENCES FOR PROJECTS
At HAYN CONSULTING d.o.o., we are proud to showcase the exceptional work of our leading engineer, Petar Hajnic, during his work on projects at Dalekovod d.d. His significant contributions to multiple projects are instrumental in delivering outstanding results for the company. Petar Hajnic holds official references and documentation for each project, emphasizing his expertise and commitment. Below, you’ll find detailed descriptions of his roles and contributions on various projects, illustrating the value he brought to Dalekovod d.d. and the engineering sector.
Construction of the Section DC 403 – from Škurinje to the port of Rijeka related to equipping the road and tunnel Podmurvice
Completed between October 2021 and 2023 by Hrvatske ceste d.o.o., the Podmurvice road tunnel project focused on enhancing safety and operational efficiency under expert leadership. Petar Hajnic role’s was Project Manager and Site Engineer.The project featured advanced tunnel lighting and ventilation to ensure safety in main pipes and emergency exits. A robust backup power system and a secure 20kV power supply were implemented for uninterrupted functionality. Comprehensive 20/0.4kV power distribution supported seamless operations. Additionally, integrated transport systems and state-of-the-art fire alarms were installed for superior management and safety. Beyond the tunnel, roadway enhancements included strategic lighting and cutting-edge traffic equipment to boost road safety and efficiency.

Reconstruction – existing and construction of the second track of the railway line on the section Dugo Selo - Križevci
Since 2016, under the guidance of HŽ Infrastruktura and expertly managed by Petar Hajnic as Project Manager, this ongoing project focuses on upgrading railway infrastructure for efficiency and safety. The initiative covers power subsystem construction and reconstruction to boost operational performance. Advanced traffic control and signaling systems are being implemented to ensure improved safety and efficient traffic flow. Additionally, effective noise protection measures are designed and installed to reduce environmental impact and improve community comfort, demonstrating a commitment to sustainable and community-friendly infrastructure development.

Equipping the Expressway – new installations, traffic signals and equipment of the section Vrbovec 2 – Farkaševac
From 2017 to 2019, Hrvatske autoceste d.o.o. led an initiative to enhance the expressway section from Vrbovec 2 to Farkaševac. Petar Hajnic had to roles for electrical part as project manager and chief engineer. The project involved constructing new medium voltage installations paired with a 20/0.4kV substation to ensure reliable power supply. Junction lighting was improved to enhance visibility and safety.Additionally, the implementation of traffic signalization and equipment upgrades optimized traffic flow and safety, marking a significant step forward in modern expressway management.

Equipping of the Beli Manastir – Osijek – Svilaj – Ploče Motorway-section Osijek-Drava Bridge
Between 2016 and 2018 Hrvatske autoceste d.o.o. invested in significant infrastructure upgrades were made to the Drava Bridge. Petar Hajnic was in role’s of Project Manager and Chief Engineer. The relocation of 20kV and 35kV medium voltage installations was conducted to support future substations along the AC route, upgrading the energy infrastructure. A photovoltaic system was installed to promote sustainable energy use. To ensure safety and visibility, a reliable backup power supply and effective pylon lighting were implemented. Additionally, decorative lighting enhanced the aesthetic appeal of the bridge.Comprehensive traffic signalization and equipment upgrades were applied, optimizing traffic management and ensuring improved flow and safety.

Equipping the Expressway – New installations, traffic signals and equipment of the Gradec – Križevci section
From 2015 to 2016 essential advancements were made in road infrastructure by Hrvatske autoceste d.o.o.The installation of advanced traffic signalization and equipment significantly enhanced road safety and traffic flow. Comprehensive road lighting solutions were implemented to improve visibility and ensure safer roadways and all under supervision of Petar Hajnic who had two role’s on this project, one as Project Manager and another as Chief Engineer.

HEP Distribution – 4-year contracts for the construction and maintenance of the power system
During the period of 2014 to 2015, under the role of Project Manager and Construction Site Engineer Petar Hajnic was responsible for specialized maintenance and construction of electrical systems were undertaken.Investor was HEP ODS.The focus was on high-quality electrical installation works, ensuring optimal performance and reliability. Through careful planning and execution, the project successfully met industry standards, reinforcing the importance of quality in electrical system infrastructure.

Zagreb-Sisak Motorway – section Buševec-Lekenik
From 2012 to 2015 Hrvatske autoceste d.o.o., made significant improvements on the Zagreb-Sisak Motorway, specifically the Buševec-Lekenik section. Petar Hajnic role was Site Engineer. The project included the power supply and installation of new 20/0.4kV substations, ensuring reliable energy distribution throughout the area. Comprehensive lighting solutions were implemented for junctions and road rest areas, enhancing visibility and safety for all travelers. Additionally, advanced telecommunications installations (DTK) were introduced to facilitate efficient connectivity. Effective traffic equipment and signaling systems were also implemented, significantly improving road safety and traffic management with state-of-the-art solutions.
Construction of the Second Phase of the Velika Gorica – bypass on the D31 with a connection to the D408
From 2015 to 2016 essential advancements were made in road infrastructure by Hrvatske autoceste d.o.o.The installation of advanced traffic signalization and equipment significantly enhanced road safety and traffic flow. Comprehensive road lighting solutions were implemented to improve visibility and ensure safer roadways and all under supervision of Petar Hajnic who had two role’s on this project, one as Project Manager and another as Chief Engineer.
Zagreb-Sisak Motorway- section Jakuševec-Velika Gorica
From 2009 to 2015, Petar Hajnic was Site Engineer on the project and Hrvatske autoceste were investor. The project involved the power supply and installation of new 20/0.4kV substations, providing reliable energy solutions crucial for ongoing infrastructure projects. The relocation of existing medium voltage (MV) and low voltage (LV) installations optimized utility networks for improved functionality.Advanced telecommunications installations were implemented to enhance connectivity throughout the area. Comprehensive lighting solutions for nodes ensured visibility and safety at key junctions. Additionally, state-of-the-art video surveillance systems were introduced to bolster security through effective monitoring.
Highway Beli Manastir – Osijek – Svilaj – Ploče, section Osijek-Đakovo
During the period from 2008 to 2009, Hrvatske autoceste d.o.o. investor on the project made key enhancements to modern infrastructure.The project on which Petar Hajnic was in a role of Site Engineer, focused on the power supply and installation of new 20/0.4kV substations, ensuring robust energy solutions necessary for contemporary infrastructure needs. The relocation of existing medium voltage (MV) and low voltage (LV) installations streamlined utility networks, boosting overall performance.Advanced telecommunications installations were developed to improve connectivity. Node lighting solutions were implemented to enhance safety and visibility at critical junctions. Additionally, state-of-the-art video surveillance systems strengthened security through effective monitoring.Comprehensive traffic equipment and signalization optimized traffic management and safety, utilizing innovative signaling technologies to improve overall transportation efficiency.
Macelj Border Crossing
From 2008 to 2011, Hrvatske autoceste d.o.o. invest in one of the most important project at that time at Macelj Border Crossing at the time when car tourism was exploding. Petar Hajnic was appointed in a role of Works Manager.The project included the power supply and installation of a new 20/0.4kV substation, delivering reliable energy solutions tailored to meet infrastructure needs. The relocation of existing medium voltage (MV) and low voltage (LV) installations enhanced the efficiency of utility networks, optimizing overall performance.Additionally, comprehensive lighting solutions were implemented at border crossings, significantly improving safety and visibility at these critical points. These initiatives not only bolstered infrastructure reliability but also catered to the needs of travelers and the surrounding community.